HDD / Bahrain

220 KV REINFORCEMENT AND DIVERSION CABLE WORK & 400KV LOOP CIRCUIT- PACKAGE B2

12777.29 Mtr, Total 37 Crossings / Bundle of 200 mm +110 mm / ELECTRICITY & WATER AUTHORITY (EWA) / Bahrain

Back to Middle East Projects
Project Overview

Execution & Technical Scope

Reinforcement an diversion cable work with loop cicuit.

Site Photos & Visual Records

220 KV REINFORCEMENT AND DIVERSION CABLE WORK & 400KV LOOP CIRCUIT- PACKAGE B2 site operation

Key Statistics

  • Length12777.29 Mtr, Total 37 Crossings
  • DiameterBundle of 200 mm +110 mm
  • EquipmentVermeer 130 x 150, DD6
  • Client / OwnerELECTRICITY & WATER AUTHORITY (EWA)
  • LocationBahrain
  • Year Completed2020