HDD / Jizan Ksa

MGS Expansion Phase -3 ,Package 17

733.80 Mtr / 30'' Steel pipe +4'' Hdpe Pipe / KPIL / SAUDI ARAMCO / Jizan Ksa

Back to Middle East Projects
Project Overview

Execution & Technical Scope

Trenchless Engineering Services Co. Ltd. was awarded the Package 17 HDD scope by K.P.I.L. as part of the Master Gas System Expansion Phase 3. The scope involves installation of a 30" steel pipeline along with two 4" HDPE pipes in the Jijan cluster area. Two road/highway crossings were executed, measuring 408 m and 325 m respectively, at a depth of 12 m, crossing various utilities along the route. The work was carried out using a DD440 rig spread.

Site Photos & Visual Records

MGS Expansion Phase -3 ,Package 17 site operation

Key Statistics

  • Length733.80 Mtr
  • Diameter30'' Steel pipe +4'' Hdpe Pipe
  • Depth12 Mtr
  • GeologySand and Silt
  • EquipmentDD 440 American Auger Drilling Rig
  • Client / OwnerKPIL / SAUDI ARAMCO
  • LocationJizan Ksa
  • Year Completed2026